Optics and Commissioning (1)

4
18 Dec 2006, 13:30
meeting room, 1F, 3-gokan (KEK)

meeting room, 1F, 3-gokan

KEK

1-1 Oho, Tsukuna-shi, Ibaraki-ken, Japan, 305-0801

Description

(1) New extraction line tuning (coupling and dispersion
correction) We must
evaluation and decide the strength of the skew
quadrupoles for the tuning.
(2) Recent ATF2 FF optics (modified quadrupole position
at last project
meeting).
We must fix the final ATF2 FF optics.
(3) BBA and optics diagnostics. I believe many
collaborators are interested
in
this study item. We need to start the preparation of the
optics diagnostics.
(4) Beam size tuning without Shintake monitor. Since
the dynamic range of
Shintake monitor is less than few hundred nm beam
size, we must make
the
beam size less than sub-micron w/o Shintake monitor.
This item is one of
the
important issues for ATF2 commissioning.
(5) Final beam size tuning.
(6) International collaborations.

Presentation materials

There are no materials yet.
Previous tabNext tab
Print
PDF
Full screen
Detailed view
Filter
13:00
14:00
15:00
Mark Woodley
Recent status of new extraction line and the requirement of the skew quadrupole strength
meeting room, 1F, 3-gokan, KEK
13:30 - 14:10
Rogelio Tomas
Preliminary skew quadrupole requirements for vertical dispersion correction in ATF new EXT
meeting room, 1F, 3-gokan, KEK
14:10 - 14:20
Dr Toshiyuki Okugi
Coupling Correction fot ATF2 extraction line
meeting room, 1F, 3-gokan, KEK
14:20 - 14:25
Mark Woodley
ATF2 Layout/Optics
meeting room, 1F, 3-gokan, KEK
14:25 - 14:45
Dr Glen WHITE
Simulation of Alignment and Tuning for ATF2 FF
meeting room, 1F, 3-gokan, KEK
14:45 - 15:05