Meeting about LDC integration
  • Wednesday, 5 September
    • Forward Region 3/304

      3/304

      DESY Hamburg

      Introduction
      LDC V5
      Current Opening Scenario
      * Support Tube
      * Length/Position Shielding Tube
      LumiCAL
      * Support LumiCAL
      * Installation LumiCAL
      BeamCAL
      * Position BeamCAL (Constrains etc.)
      Vacuum
      * Pump
      * Valves
      * Flanges

    • Services 3/304

      3/304

      DESY Hamburg

      Power needs
      Cooling needs
      Other services needed (Gas, etc.)

    • Others 3/304

      3/304

      DESY Hamburg

  • Thursday, 6 September
    • Mechanical Detector Concept 1c/134

      1c/134

      DESY Hamburg

      Current Opening Scenario
      * Max. Opening (beam; garage, TPC exchange, ...)
      Yoke End Cap Concept
      * Split?
      * Tolerable Bending
      QD0
      * Support
      * Supply
      Surface Assembly

    • Hall dimension/layout 1c/134

      1c/134

      DESY Hamburg

      Pacmann
      Platform
      Crane capacity
      Hall dimensions

    • 12:00
      lunch break Canteen

      Canteen

      DESY Hamburg

    • Talks for IRENG 1c/134

      1c/134

      DESY Hamburg