    • 3.9 GHz
      • 1
        Cavity No 8 vertical test results
        Speaker: Timer
      • 2
        Schedule for welding helium vessel to cavity No. 5
        Speaker: Foley
      • 3
        Cavity No. 7 vertical test schedule
        Speaker: Harms, Rowe
      • 4
        Overview of 3.9 GHz single-cell program
        Speaker: Cooley
      • 5
        Coupler progress
        Speaker: Olis
      • 6
        Other business
    • 1.3 GHz
      • 7
        Planned visit to AES
        Speaker: Foley
      • 8
        Cavity orders for FY2008
        Speaker: Champion
      • 9
        Potential material order(s) for FY2008
        Speaker: Champion
      • 10
        Other Business