09:00
Machining of helium vessel for cavity No. 5
-
Foley
-
09:15
Progress on remaining helium vessels
-
Mitchell
-
09:30
TIG welder certification
-
Foley
-
09:40
Cavity No. 7 main coupler flange issues
-
Olis, Rowe
-
09:50
Schedule for processing cavity No. 7
-
Harms
-
10:00
Other business