3.9GHz Engineering meeting

US/Central
The Hermitage

The Hermitage

    • 3.9 GHz
      • 1
        Status of helium vessel order from Hi- Tech: estimated delivery date
      • 2
        Cavity No. 5 status
        Speaker: Timer
      • 3
        Discussion of Zanon question concerning possible change in design of end group(s) for 9-cell cavities
      • 4
        Procedure for welding helium vessel to cavity No. ? EB welding time at Sciaky
      • 5
        Status of parts for dressing cavities
      • 6
        Shipping update
      • 7
        Re-assignment of staff
      • 8
        Status of single-cell cavities
        Speaker: Foley
    • 1.3 GHz
      • 9
        Revised quote from AES for six nine-cell cavities -- order status
        Speaker: Foley
      • 10
        Cancellation of order to AES for six 9-cell cavities