69th ATF2 meeting

January 23 14:30- 16:30, ATF LC meeting room at KEK.

1. Quadrupole Magnet Installation in the ATF2 Beam Line, R. Sugahara(KEK)

file , pdf (4 pages, 1.1MB)

19 quadpole-systems were successfully installed for 7 through 9 January 2008, where 19 concrete base blocks have been installed for 10 through 20 December, 2007. Actually, 22 movers were installed in total, while 3 sextupoles and 3 dipoles were not installed because of the delay of magnets arrival and T-1 mounts, respectively. The three T-1s arrived at Narita airport last Sunday.

One of the quadrupoles was misplaced by 5cm along the beamline. Its baseplate will be modified.

Also, the dynamic range of FFTB mover was measured.

C : The work is very impressive and nice !

2. Update of the intermediate beta optics at IP, Sha Bai (LAL, IHEP)

file , pdf (4 pages, 56kB)

S.Bai updated her study which has been presented at the 5th ATF2 project meeting. This study estimates the maximum normalized integrated strengths ( unit in 1/m) for the ATF2 Final Doublet quadrupoles in the intermediate beta optics at the focal points of -54cm and +39cm for Honda monitor and carbon wire scanner, respectively, as well as IP. Especially, she found that the QD0 strength exceeds the maximum to focus the beam to a waist at the Honda monitor, for both the nominal beta function and enlarged values, that is -2.2 compared with the maximum of -1.5275.

Within this limit, the maximum distance is estimated to be -16cm from IP for the nominal beta function.

Q : What is the maximum current of power supply for the case of the nominal beta function at -54cm ( Honda monitor ) ? If the current is sufficiently supplied, the nominal beta function can be achieved. Is it right?
A : Yes, if the magnet (QD0) can be operated. The current would be proportional to the strength.
Q : What is the strength (K-value) of QD0?
A : It is 2.2, which should be less than the maximum of 1.5275.
C : The power supply has 150A max.
Q : What is the beam size in this case?
A : It is the nominal size, i.e. 38nm as presented at the 5th ATF2 project meeting.

Reminding the motivation of this study, P.Bambade commented in his recent e-mail as follows; "In what we did we thought we should preserve as much as possible the basic optical features of the final focus (especially its internal symmetries), so we changed the input match and only adjusted the effective focal length of the FD (and readjusted the sextupoles) inside the final focus. In this way, the focal point at the Honda monitor (for any of the chosen beta*_y values) results from a configuration which is closely related to the nominal one. Hence all the work to move the waists in x and y by 54 cm longitudinally is done by the FD.

However, we believe that it must be possible to achieve similar conditions at the Honda monitor, within the existing ranges for QD and QF (hence not require to upgrade the QD power supply) if we also use some of the other quads within the final focus to help the FD, and then forget about keeping its properties. Probably for large beta*_y values with spot sizes matched to the resolution of the Honda monitor, the quality of the chromatic correction is less important anyway. However, would it be appealing to do that ? What would we really learn from tuning the beam at the displaced IP in such a condition, that could be extrapolated meaningfully to the nominal IP ?"

3. Status of FD-magnets and sextupoles , C. Spencer (SLAC)

file , pdf (21 pages, 1.6MB)

Special pole-side shims have been designed and are being prepared, because the FD magnets ( QD0 and QF1) have too large 12 pole components. It is expected that the 12 pole component will be 0.02% at r=1cm with the special shims. The shims will be fabricated in next 2 weeks, and they will be assembled in QD0 by 4 February 2008. The goal is to ship the FD magnets to LAPP by middle of March, 2008.

Cooling pipes for two sextupoles (SD0, SF1) will be shipped to LAPP. The old FFTB sextupoles will be shipped from KEK to LAPP soon. C.Spencer is working on administrative paper works for the shipment.

The three FF-sextupoles (old SLC magnets) will be refurbished and re-measured at SLAC and then shipped to KEK. The BPM mount will be prepared by Honda. The supports of these FF sextupoles magnets are being designed and will be made at SLAC.

Q : Could you send drawings of Sugahara's adjuster plate and position adjustment support ( they sit on the FFTB mover), so SLAC can design its support to fit in. Where the support is put ?
A : Yes. Actually, the gadjuster plateh is the same as that for QEA-magnets.
Q : Anyway, please send the drawings.
A : Yes.
Q : Where are water manifolds placed for FD Quads ?
A : They can be mount on the wall near the FD table. KEK will prepare them. (Later comment from Spencer - we need to discuss this in detail, SLAC would have to provide some water fittings you cannot buy in Japan)
Q :QC3 has 12 tooling ball positions. General question would be : can enough of them be seen with the Shintake monitor and its support structure ?
Q : The KEK target holder seems to be 30mm diameter ball. It is too big.
A : We (KEK) have half inch ball. So, we will make new holder .
Q : How to get offset of the tooling balls ? Please provide the coordinates of the magnet center and mechanical centers of the tooling balls.
A : SLAC alignment group has the information, or will generate this fiducialization data. So, Spencer will provide this information.
Q : How much is actual floor hight at ATF2 area ?
A : The floor was lowest in the middle. It may sink with beam dump .
A : Sugahara will take care of floor height.
C : Right after this meeting, Sugahara measured the floor level. His report is listed below;

4. update of lists for QBPM electronics system, A. Seryi (SLAC)

J.May and D.McCormick are preparing documents and instruction for the movers, the QBPM electronics system and the carbon wire scanner.
Q :

5. KEK site meeting

Cable trays and cabling will be installed in a coming month. The concrete shields will arrive in middle of February for a month from the company. The shields will be installed by end of March 2008. The beam dump will be installed in March or April.

Before the shield-work, we would like to install QBPMs inside the magnets. This work can be done with portable crane of 1 ton.

A chain block crane will be set on the side-wall for works inside of the shield.

Status of Shintake monitor support, T. Kume (KEK)

file , pdf (Japanese) (7 pages, 458kB)

Status and installation/alignment method of the Shintake monitor were presented. It was reminded that the floor is not flat to be seriously considered . We continue to discuss on these issues.