3.9GHz status

US/Central
The Hermitage

The Hermitage

    • 1
      Status of helium vessel order from Hi-Tech; estimated delivery date for first helium vessel
      Speaker: Alsip
    • 2
      Proposed schedule for welding helium vessel to cavity No. 3
      Speaker: Foley
    • 3
      Cavity No. 5 horizontal test schedule
      Speaker: Rowe
    • 4
      Cavity No. 7 vertical test schedule
      Speaker: Rowe
    • 5
      Status of 3.9 GHz cryomodule pressure vessel and piping safety testing and documentation
      Speaker: Carter
    • 6
      Comments on 3D RF computational model of 3.9 GHz cavities and proposed design changes to improve performance of cavities to be fabricated by Zanon
      Speaker: Solyak
    • 7
      Other business