3.9GHz status
Monday, 17 November 2008 -
09:00
Monday, 17 November 2008
09:00
Status of cavities 3, 4, 5,6,7 and 8
Status of cavities 3, 4, 5,6,7 and 8
09:00 - 09:20
Room: The Hermitage
09:20
Piping issues
Piping issues
09:20 - 09:40
Room: The Hermitage
09:40
PAC 2009 Abstracts
PAC 2009 Abstracts
09:40 - 10:00
Room: The Hermitage
10:00
Equipment needed for ACC39 acceptance tests
Equipment needed for ACC39 acceptance tests
10:00 - 10:20
Room: The Hermitage
Discuss what equipment FNAL needs to provide for electrical acceptance tests of ACC39 at DESY. Mating connectors cables, breakout boxes, etc.?
10:20
Other business
Other business
10:20 - 10:40
Room: The Hermitage