February 2012 9mA Studies

Europe/Zurich
Universe

Universe

Description
DESIRED MACHINE CONDITIONS * Long bunch trains (600us or more) * 3MHz bunch rep rate, range of bunch charges up to 2nC/bunch * Range of gradients on ACC67 up to cavity quench limits OVERALL GOALS * Study beam operation at maximum achievable gradients on ACC67 with light beam loading * Study setting up flat gradients on all cavities in ACC67 with heavy beam loading (continuation of ‘Pk/Q’l’ study) * Eventually: Operate as close as possible to gradient limits on ACC67 with heavy beam loading * Klystron saturation studies with heavy beam loading The nominal program for each shift is included in the notes for each shift. These will be updated as needed
Link to searchable database of DAQ channels
LLRF scaling factors for Feb 2012
    • 07:00 15:00
      Morning (Maintenance) 8h
      Switch laser to 3MHz Switch machine operating rate to 5MHz
      Notes from daily coordination meeting
    • 15:00 23:00
      Afternoon 8h
      TPS validation Machine setup for long bunch trains at 3MHz and 5Hz Energy: 1GeV
    • 23:00 07:00
      Night 8h
      Machine tuning: aim for ≥1nC/bunch at 3MHz, 600us bunch trains
    • 07:00 15:00
      Morning 8h
      Beam loading compensation setup Piezo tuner setup Measurements of ACC67 quench limits
      Notes from daily coordination meeting
    • 15:00 23:00
      Afternoon 8h
      Pk/Ql studies at ≥3mA
      Pk/Ql shift summary
    • 23:00 07:00
      Night 8h
      1. Continue Pk/Ql studies at 3mA/600us as needed 2. Injector matching for 2nC bunches, starting around 04:00 3. Parasitically, perform initial gradient limit measurements
    • 07:00 15:00
      Morning 8h
      1. Once injector matching is completed at 2nC, begin transporting 2nC bunches and long bunch trains to the end of the linac 2. Return to high gradient studies: measure gradient limits without beam, then measure with light beam loading
      Quench shift summary
    • 15:00 23:00
      Afternoon 8h
      Preparation for Klystron saturation / RF power overhead studies Pk/QL studies at ≥4mA
    • 23:00 07:00
      Night 8h
      Machine tuning: aim for 2nC/bunch @ 3MHz, 600us bunch trains
    • 07:00 15:00
      Morning 8h
      Test procedures for performing gradient scans (+/- few %) with 6mA and 600us bunch trains
      Pk/Ql shift summary
    • 15:00 23:00
      Afternoon 8h
      High gradient studies with light beam loading
      Quench shift summary
    • 23:00 07:00
      Night 8h
      Pk/Ql studies at 6mA and long bunch trains Set up for 8hr stable run with gradients close to quench and moderate beam loading
    • 07:00 15:00
      Morning 8h
      8hr stable run with high gradients and beam loading
    • 15:00 23:00
      Afternoon 8h
      High gradient studies Set up for RF power overhead studies
    • 23:00 07:00
      Night 8h
      RF power overhead studies
      document
      Near kly. saturation
    • 07:00 15:00
      Morning 8h
      Set up high gradient studies with heavy beam loading High gradient studies with heavy beam loading
    • 15:00 23:00
      Afternoon 8h
      High gradient studies with heavy beam loading
    • 23:00 07:00
      Night 8h
      High gradient studies with heavy beam loading