HLRF Technical System Weekly Meeting
Thursday 24 Aug 2006, 03:00
→
05:00
US/Pacific
SLAC: SCS 115, 3-5PM PDT (High Level RF TS Review)
SLAC: SCS 115, 3-5PM PDT
High Level RF TS Review
Description
1. Review status of major HLRF subsystem, components in Baseline Conceptual Design. 2. Review progress of RDR Cost Modeling and Estimates, resource assignments, standard methodologies. 3. Review R&D progress for Alternate Conceptual Designs.
03:00
→
03:10
Agenda & Goals
10m
Speaker
:
Raymond Larsen
(
SLAC
)
document
pictures
Slides
03:10
→
03:20
KEK Progress
10m
Speaker
:
Dr
Shigeki Fukuda
(
KEK
)
03:20
→
03:30
Main Linac & Klystron Status
10m
Speaker
:
Chris Adolphsen
(
SLAC
)
03:30
→
03:40
Distribution System Progress
10m
Speaker
:
Dr
Chris Nantista
(
SLAC
)
03:40
→
03:50
Waveguide 3D Modeling
10m
Speaker
:
Jerry Leibfritz
03:50
→
04:00
Distribution Costs
10m
Speaker
:
Mike Neubauer
(
SLAC
)
04:00
→
04:10
Modulator Progress
10m
Speakers
:
Chris Jensen
(
FNAL
)
,
Clay Corvin
(
SLAC
)
04:10
→
04:20
Controls/Interlocks/Protection Status
10m
Speaker
:
Richard Cassel
(
SLAC
)
04:20
→
04:30
Racks & Cooling
10m
Speaker
:
Robert Downing
(
SLAC
)
Slides