3.9GHz Engineering meeting

US/Central
The Hermitage

The Hermitage

Minutes
    • 09:00 09:40
      1.3 GHz
      • 09:00
        RRR test results on "drop offs" from cells 3, 5 and 7 of AES-001 15m
        Speaker: Cooley
      • 09:15
        Plans to have JLab X-ray NbTi used on AES cavity flanges 15m
        Speaker: Foley
      • 09:30
        Requirement for inclusion of attachment rings on single-cell cavities -- Americanization of DESY drawings 10m
    • 09:40 10:35
      3.9 GHz
      • 09:40
        Status of cavities 7 and 8 10m
        Speaker: Foley
      • 09:50
        Single-cell cavity fabrication status and plans 10m
        Speaker: Foley
      • 10:00
        Helium vessel issues -- material and welder certification -- procedure -- testing, etc. 15m
        Speaker: Helen, Mitchell, Champion, etc
      • 10:15
        Single-cell cavity test results 10m
        Speaker: Genfa
      • 10:25
        Plasma processing plan for 3.9 GHz 10m
        Speaker: Genfa
    • 10:35 10:45
      OTHER BUSINESS
      • 10:35
        1.5 GHz single-cell cavity from "bad" material 10m
        Speaker: Genfa