Major issues are listed below;
(1) Readiness and integration of control software
(2) Commissioning schedule, taking into account a variety of issues, including:
o the funding situation facing the collaboration;
o a wide-ranging R&D program, and high-visibility goals for ATF2;
o the range of different optics required for different beam studies;
o the reproducibility of optics and good beam quality required for ATF2;
o scheduling of meetings;
o external timing constraints (e.g. for completion of PhD theses).
(3) Detailed planning of longer-term studies.
It will be important to know the schedule for studies of fast extraction kickers, to be able to define the commissioning schedule for ATF2.
The expected outcome of this meeting would be an optimized strategy and an
overall schedule which would allow efficient ATF2 commissioning and minimized
interference with various short and long term studies at ATF.
09:00
→
12:00
Integration of software in the ATF control system
beam tuning and hardware
flight simulator
09:00
Present Status of Hardware-direct Software R&D30m
Speaker:
S.Boogert
Slides
09:30
Present Status of High-Priority Software R&D30m
Speaker:
C.Rimbault
Slides
10:00
Present Status of Flight Simulator30m
Speaker:
G.White
Slides
10:30
break
30m
11:00
Present Status of Near-Future Study30m
Speaker:
S.Kuroda
Slides
11:30
Discussion20m
Speaker:
All
12:00
→
13:30
Lunch
1h 30m
13:30
→
14:10
DR-emittance R&D40m
Speaker:
DrKiyoshi Kubo(KEK)
Beam time proposal
DR emittance
14:10
→
14:50
Plan of fast kicker R&D40m
Speaker:
MrTakashi Naito(KEK)
Slides
14:50
→
15:20
coffee break
30m
15:20
→
16:30
Commissioning schedule
strategy ; goals, team works,
schedule by end of 2008 and also in 2009
15:20
IP-BSM beam study in Dec.200815m
Speaker:
MrMasahiro OROKU(Tokyo Univ.)
Paper
15:35
Beam time request from SLAC team15m
Speaker:
DrAndrei Seryi(SLAC)
Slides
15:50
ATF2 beam commissioning plan15m
Speaker:
DrToshiyuki Okugi(KEK)
Slides
16:05
Discussion for the beam time schedule25m
Exel file
16:30
→
16:40
coffee break
10m
16:40
→
17:40
BDS status and plan
what will be coming out from ATF2
16:40
BDS and ATF220m
Speaker:
DrAndrei Seryi(SLAC)
Slides
17:00
ATF2 magnet and PS lessons for ILC BDS10m
Lessons learned from designing, fabricating & installing ATF2 magnets and their power supplies that should be remembered for same tasks for the ILC’s BDS