Major issues are listed below;
(1) Readiness and integration of control software
(2) Commissioning schedule, taking into account a variety of issues, including:
o the funding situation facing the collaboration;
o a wide-ranging R&D program, and high-visibility goals for ATF2;
o the range of different optics required for different beam studies;
o the reproducibility of optics and good beam quality required for ATF2;
o scheduling of meetings;
o external timing constraints (e.g. for completion of PhD theses).
(3) Detailed planning of longer-term studies.
It will be important to know the schedule for studies of fast extraction kickers, to be able to define the commissioning schedule for ATF2.
The expected outcome of this meeting would be an optimized strategy and an
overall schedule which would allow efficient ATF2 commissioning and minimized
interference with various short and long term studies at ATF.
Integration of software in the ATF control system
beam tuning and hardware
flight simulator
1
Present Status of Hardware-direct Software R&D
Speaker:
S.Boogert
Slides
2
Present Status of High-Priority Software R&D
Speaker:
C.Rimbault
Slides
3
Present Status of Flight Simulator
Speaker:
G.White
Slides
10:30
break
4
Present Status of Near-Future Study
Speaker:
S.Kuroda
Slides
5
Discussion
Speaker:
All
12:00
Lunch
6
DR-emittance R&D
Speaker:
DrKiyoshi Kubo(KEK)
Beam time proposal
DR emittance
7
Plan of fast kicker R&D
Speaker:
MrTakashi Naito(KEK)
Slides
14:50
coffee break
Commissioning schedule
strategy ; goals, team works,
schedule by end of 2008 and also in 2009
8
IP-BSM beam study in Dec.2008
Speaker:
MrMasahiro OROKU(Tokyo Univ.)
Paper
9
Beam time request from SLAC team
Speaker:
DrAndrei Seryi(SLAC)
Slides
10
ATF2 beam commissioning plan
Speaker:
DrToshiyuki Okugi(KEK)
Slides
11
Discussion for the beam time schedule
Exel file
16:30
coffee break
BDS status and plan
what will be coming out from ATF2
12
BDS and ATF2
Speaker:
DrAndrei Seryi(SLAC)
Slides
13
ATF2 magnet and PS lessons for ILC BDS
Lessons learned from designing, fabricating & installing ATF2 magnets and their power supplies that should be remembered for same tasks for the ILC’s BDS