ATF2 weekly meeting

Asia/Tokyo
Draft Minutes 7/27
    • 14:30 15:50
      International phone/webex meeting
      • 14:30
        Study of the calibration of individual strip-line electrodes 20m
        (pedestal, > non-linear response) with and without firing the kicker + any further > analysis / improvements of the electronics
        Speaker: Mr Yves Renier (LAL)
        Slides
      • 14:50
        Discussion of beam schedule in this October and November 40m
        Installations, hardware checkouts and machine studies It is necessary for planning travel to KEK for oversea's colleagues.
        • Personal strategy for ATF2 beam operation in 2009 5m
          Speaker: Dr Toshiyuki Okugi (KEK)
          Slides
        • Installation plan in this summer shutdown 5m
          Speaker: Nobuhiro Terunuma (KEK)
    • 15:30 16:30
      KEK site meeting (Japanese)
      • 15:30
        Progress of Shintake monitor work 20m
        Speakers: Mr Masahiro OROKU (Tokyo Univ.), Mr Takashi Yamanaka (The University of Tokyo)
        Time: 17:30(JST) - Site: KEK ATF LC container Participants: Tauchi, Terunuma, Okugi, Kuroda, Naito, Yamanaka, Kamiya(WebEx), Oroku(WebEx) * Plan to enlarge the present IP laser hut to contain a new IP-BSM laser - Power supply: Current one can be used by switching - Cooling water: No additional chiller inspect whether the present chiller can be used for both lasers - Optical table: Bigger table can be used. - After the expansion of the laser hut, it is inevitable to share the same laser hut with MONALISA group. - It is desired to separate the laser hut. (prepare a setup to divide the hut) * Decision of Beam Optics - Beam current: higher is better - Repetition rate: faster is better Naito-san will try to prepare the hardware for 3 Hz operation. - Horizontal beam size: don't want to focus further (last time: sigma_x = 10 um) It was observed the background become larger during Q-scan using QD0 - Vertical beam size: - At first, 4..58 deg crossing angle, 6.7 um fringe pitch will be used in the interference mode - to observe the fringe pattern by the Compton photon signal, less than 1 um beam size is desired. * New laser - specification of the laser is fixed. - it will be delivered to KEK end of September.