9mA Experiment meeting: Coordination meeting for LLRF activities during Aug/Sept shutdown
→
Europe/Berlin
24/200 (DESY/WebEx)
24/200
DESY/WebEx
Description
LLRF systems should be ready for 9mA beam studies by Monday August 31st (end of week-2 of the shutdown).
Week-1 of the shutdown (Aug 17-Aug24) will be open access with no studies time.
Week-2 (Aug 24-31) gives opportunity for RF studies overnight. These studies will be used for final commissioning and RF/LLRF system setup.
Please be prepared to talk to the work you anticipate for the shutdown and the draft readiness checklist and studies outline linked from here