Site: KEK ATF LC Container
Time: 16:00(JST) ~
Participants: T. Tauchi, N. Terunuma, J. Urakawa, T. Okugi, S. Kuroda, K. Kubo, P. Bambade,
S. Boogert, A. Aryshev, T. Yamanaka, Y. Kamiya(WebEX)
* Modification of the IP target insertion stage
C: Support of the stage using screws should be three.
Micrometers won't be able to bear the preassure from vacuum
* Detector Interlock
C: When the PMT signals are used to interlock the HV to the detector,
You should use a discriminator rather than charge ADC reading.
If the gate signal to the ADC is not adjusted, it is probable to miss
the high current signal.
Q: If the local machine is stopped by some troubles, HV state cannot
be changed and screen monitors cannot be inserted?
A: In this case, they can be movable by changing the EPICS record forcibly.
C: In practice, PLC should be used instead of a PC to make the system reliable.
Q: How long does it take to stabilize HV after swtching on?
A: If the HV is not so high, it takes 5 minitues or so.
C: If screen monitors and wire scanners are used often, that period becomes
a waste of time. If you can prepare a movable lead block, it will be better
than HV interlock. (HV interlock should be also prepared.)
* Laser Replacement
C: Is one day enough to set up a new laser? If a company can make it, you
should prepare plenty of time (from the afternoon of September 24) for
laser set up.