9mA Experiment meeting: Coordination meeting for LLRF activities during Aug/Sept shutdown

Europe/Berlin
24/200 (DESY/WebEx)

24/200

DESY/WebEx

Description
LLRF systems should be ready for 9mA beam studies by Monday August 31st (end of week-2 of the shutdown). Week-1 of the shutdown (Aug 17-Aug24) will be open access with no studies time. Week-2 (Aug 24-31) gives opportunity for RF studies overnight. These studies will be used for final commissioning and RF/LLRF system setup. Please be prepared to talk to the work you anticipate for the shutdown and the draft readiness checklist and studies outline linked from here
Minutes
Slides
    • 15:00 15:25
      LLRF Studies outline for KW31 (August 24-31) 25m
      Please review the attached studies outline before the meeting
      Speaker: Mr John Carwardine (Argonne)
      Draft studies outline
    • 15:25 15:50
      LLRF system readiness check-off 25m
      Please review the draft checklist before the meeting
      Draft LLRF readiness checklist