ATF2 Commissioning Monthly Meeting

Asia/Tokyo
Andrei's milestones
ATF Operation Meeting
call your contributions by T.Okugi
Published milestones
Summay (draft, 10 Jan.2009)
    • 14:30 15:30
      Commissioning Team Meeting

      Webex sytem : https://fnal.webex.com/

      • 14:30
        Summary of commissioning schedules and comments from colleagues 20m
        -Global and monthly milestones -necessary steps ( both hardware and software commissioning ) to achieve milestones -Detailed schedule by summer 2009 as much as possible -new QM7R installation and fast kicker installation/removement -commissioning Shintake monitor, BPMs, Carbon wire scanner -software tasks -re-alignment of beam lines ( BT and FF ) -DR emittance ( 24pm at least )
        Speakers: Philip Bambade (Laboratoire de l''Accelerateur Lineaire (LAL) (IN2P3) (LAL)), Dr Toshiyuki Okugi (KEK)
        Slides
      • 14:50
        Discussion : The milestones and schedule for 2008-2009 40m
        Exel file
    • 15:30 16:30
      KEK site meeting (Japanese)
      • 15:30
        Progress of Shintake monitor work 20m
        Speakers: Mr Masahiro OROKU (Tokyo Univ.), Mr Takashi Yamanaka (The University of Tokyo)