BDS - KOM
ROB
SLAC
-
-
09:00
→
11:20
Goals and Introduction
Introduction to the agenda and goals; the overall status of design; performance risks; R&D planned by S4; cost split of subsystems; cost drivers.
- 09:00
- 09:30
- 10:15
-
11:10
→
12:20
RDR completeness
Assess technical maturity of RDR design and completeness of the value estimate. Evaluate performance acceptability. Examine each (Tech./Global) cost and check for inconsistencies, inaccuracies, cross check with existing machines. Explain what accelerator physics requirements were driving the design and how these requirements were obtained.
- 11:10
-
12:30
→
13:30
Lunch 1h
-
13:30
→
19:00
RDR completeness
Assess technical maturity of RDR design and completeness of the value estimate. Evaluate performance acceptability. Examine each (Tech./Global) cost and check for inconsistencies, inaccuracies, cross check with existing machines.
Explain what accelerator physics requirements were driving the design and how these requirements were obtained.- 13:30
- 14:00
-
14:30
Pulsed magnets and PS 30mvia WebexSpeaker: Dr Thomas Mattison (UBC)
-
15:00
Power supplies in BDS 30mSpeaker: Mr Paul Bellomo (SLAC)
- 15:30
- 15:50
- 16:20
- 16:50
-
17:20
Vacuum system 30mvia WebexSpeaker: Dr Yusuke Suetsugu (KEK)
- 17:50
-
09:00
→
11:20
-
- 08:00 → 09:30
-
09:30
→
12:30
System integration and optimization
Quantify the worth/cost value, discuss cost drivers, evaluate performance/cost derivatives, review design decisions in terms of cost impact and discuss possibilities of further refinement.
- Aim to identify the performance driven specifications for accelerator components and especially CFS and discuss how engineering cost-performance trade-offs will be performed.
- Should include discussion of machine-detector connection and optimization, and specifically include discussion of the integrated engineering of push-pull IR, based on IRENG07 workshop, aimed to reduce the risk of performance and cost of this solution.
- 10:00
- 10:10
- 11:00
- 11:30
- 12:00
-
12:30
→
13:30
Lunch 1h
-
13:30
→
15:00
System integration and optimization 2
-
13:30
Seismic safety and life safety requirements and their effects on the design 30mSpeaker: Mr Fred Asiri (SLAC)
- 14:00
-
13:30
-
15:00
→
18:00
Options and alternatives 2
- Evaluate existing options and alternative designs and discuss their merits for the project, needed resources for development and possible timeline.
- Discussion should include e-e-, gamma-gamma, head-on and 2mrad IR designs, permanent magnet and Rutherford cable design for 14mrad IR, fixed target, muon shield, other diagnostics, crystal collimation, etc. (Time limit may force to delay some discussions).
- 15:00
- 15:30
- 16:00
- 16:30
-
17:00
Discussion 1h
-
-
09:00
→
13:00
EDR planning
Present and discuss the work packages that would cover the EDR goals of updating the ILC cost estimate, reducing the risk, reducing the cost, and preparation of the project execution plan. Discuss the WPs and their allocation process.
- 09:00
- 09:30
- 10:00
- 10:30
- 11:00
-
11:30
BDS magnet & PS 30mSpeakers: Dr Cherrill Spencer (SLAC), John Tompkins (FNAL), Mr Paul Bellomo (SLAC)
- 12:00
- 12:30
-
13:00
→
14:30
Lunch (outside of SLAC) 1h 30m
-
14:30
→
16:30
Final discussions and closeout
-
14:30
Close-out presentation 30mSpeaker: Ross, Walker
-
14:30
-
09:00
→